PMP Exam Question: Early Start begins with 1 or 0?
In the Network Diagram questions, should the diagram be started with 1 or with 0? I've seen both ways.
In the Network Diagram questions, should the diagram be started with 1 or with 0? I've seen both ways.
Comments
Hi @vmgilmore
That's a great question.
I have a blog post that addresses your question:
https://www.deepfriedbrainproject.com/2012/03/critical-path-forward-pass-calculation.html
Hope that helps.
Read my Blog | Join my Facebook page | Follow me on Twitter | Connect with me on LinkedIn
That does help. Thank you!
@vmgilmore
I have updated the blog post. In summary, I would suggestion starting with 1. Let me know if you have additional comments. Thanks.