Q. An organization is assessing 3 different projects based upon the available information, in order to evaluate the feasibility of new products or services. Which of the following is NOT a candidate for a project?
A. Renovation of a building
B. Setup of call center operations
C. Redesign of a product
D. Assembling of cars in a factory
Post your answer below.
Tagged:
Comments
B. Setup of call center operations
Hello @Blessing2014
The correct answer is "D. Assembling of cars in a factory". It's a classic example of operations.
Now coming to why it's not B - call center operations are well 'operations', but set up of the call center operations is a project.
It was one of those tricky questions, but I hope it will prepare you better for the exam.
Good luck!