Q. Procurement closure is done (choose the correct statement):
A. at the end of each project phase
B. before closing the project
C. after project closure
D. as part of the Close Project or Phase process
Post your answer below. Correct answer will be posted after receiving at least one response.
Tagged:
Comments
D
Hello @Margie
The correct answer is B - before closing the project.
Explanation: Procurement closure is done when the contract is complete, and not necessarily during the Close Project or Phase process. Procurements are usually closed before administrative closure of the project. Procurement audit is done before closing the procurement.
Reference: PMBOK® Guide, 5th Ed; Ch 12, Pg 341