Loading

Top PMI-ACP Exam Prep Tools

Difference between EAC and ETC

edited September 2012 in PM Certifications

Hello,

As both Estimate At Completion (EAC) and Estimate To Complete (ETC) related to cost forecasting. I have confusion that both are asking for how much estimated cost at that particular point from the project. Please anyone can explain in detail. Thanks

Tagged:

Comments

  • Hi @joshipiyush,

    At any given point during the project:

    • EAC is how much you expect the project to cost (total budget) when it's complete.
    • ETC is how much more money you expect to spend to complete the remaining work on the project.

    For example, initially my estimate to complete the project was $100,000 (BAC).

    2 months into the project, I have already spent $30,000, and after reviewing the remaining work, I expect to spend addition $80,000 on the project.

    So, $80,000 is my ETC, and overall the project is expected to cost $30,000 + $80,000 = $110,000. This is my EAC.

    Hope that helps.

  • Thanks Harwinder Paaji. I also wanted to know this.

    Best, KK

  • edited November 2012

    Hi everybody,

    Thanks Harwinder for his explanation and also the example. In order to get complete information on this subject, you can also study about EVM (Earned Value Management);
    in fact, there are different parameters (from basic to detail) in this area. You can first get familiar with PV, EA & AC, then the indices of Project Variance and Performance (SV, CV, SPI & CPI) and finally you can calculate the EAC & ETC (which are well explained by Harwinder).

    Thanks and regards...


    Hamed Abedi
    Management Consultant
    MAPNA (MECO)
    Tel: (+98)-26-36 63 80 01-10 (Ext. 396)
    Fax: (+98)-26-36 63 80 13
    Mob: (+98)-912-361 9768
    abedi-h@mapnaec.com
    hamed.abedi1718@yahoo.de
    https://www.mapna.com

Sign In or Register to comment.