Top PMP and CAPM Exam Prep Tools
Top PMI-ACP Exam Prep Tools
What should be the correct answer
i was going through the free sample questions one of the link and I was confused with the answer.
You are the project manager for the large Project. You are currently busy with approximating number of work periods required to complete individual activities with estimated resources. Which of the following inputs you need for this ?
1. Activity List
2. Activity resource requirements
3. Resource Calendars
4. All of the above
It says option 3 is correct. But I feel it should be option 4.
Their explanation also says "Approximating number of work periods required to complete individual activities with estimated resources is done in Estimate Activity Duration process. Activity List, Activity resource requirements and Resource Calendars are inputs of Estimate Activity Duration process. PMBOK Page no 177.'
Please give your opinion.
*Disclaimer-I believe we can discuss free sample questions on this forum.
Thanks
SK
Comments
This is the link
https://www.certchamp.com/pmp-sample-questions.jsp
Thanks
SK
The answer should be 4. It just a typo on that website specially when the explanation itself seems to suggest that 4 is correct.
We (this forum) doesn't have an issue with discussing free sample questions available publicly on the web, as long as you cite the source. It's your responsibility to make sure that you are not violating others' copyrights when you are posting the content.
Read my Blog | Join my Facebook page | Follow me on Twitter | Connect with me on LinkedIn
Thanks Harwinder for a quick reply. I saw same question on two websites stating the same option. One place, its called option and another option 3
Thanks
SK
Correction - its called option C and another option 3
Thanks
SK
That's an indicator of the quality of those sites
Read my Blog | Join my Facebook page | Follow me on Twitter | Connect with me on LinkedIn