Q. Projects are often utilized as means for achieving organization's strategic plans. Which of the following attributes would you not associate with projects?
A. Competing objectives
B. Unique
C. Temporary
D. Constrained
Post your answer below.
Tagged:
Comments
D
Hello @Himani
Welcome to PM Hangout.
The correct answer is A (Competing objectives).
Each project is unique and has a clearly defined beginning and end (temporary endeavor). Projects have competing constraints, but clearly defined objectives.
Hope it's clear.