Friends, Below question on the free 200 questions has disputed answer.
Its saying correct answer-1 and in explanation its answer 4 (which also i selected)
Give your opinions
Templates and forms which are available in the organization and are part of organization's ________ project plan development.
Assumptions
2. Constraints
3. Software
4. Methodology
Correct Answer is : 1

A is the correct answer.
Templates and forms which are available in the organization are reusable components. Any resource that can be reused as a useful tool is part of the total methodology of project planning.

Thanks
SK