Which of the below document you should refer to know with whom you will be communicating during proj
- Project Plan
- Scope Statement
- Statement of Work
- Project Charter
My answer is Project plan?
Any expert comments?
Thanks
SK
Tagged:
Comments
As communication management plan(describes communication needs) is subsidiary plan of Project management plan, I believe project plan is correct answer.
The answer was Scope Statement
Thanks
SK
And what is the reasoning by the way for Scope Stmnt? Is it because PSS contains all assumptions and constraints on a project that needs to be constantly reminded to the SHs? is this the reason. CMP is a subsidiary plan of the PMP, so I thought Project Plan is the right answer.